The upcoming phase of the Learning Commons Renovation Project involves retrofitting fire sprinklers on the second and third floors. This work will require the closure of the second floor, where library services are consolidated during the renovation. It will also impact Tutoring Services (Writing Center and LRC) and Disability Services.

The Learning Commons will close on May 19 to allow units to prepare spaces for construction and relocate services to other locations. Construction work is scheduled to begin on June 2 and be completed by the end of July 2025.

We will share more details on how services will be offered during the two-month closure in the coming weeks. In the meantime, please contact me at waydeo@hawaii.edu with your questions and concerns.