Library Renovation Project: Overview

The library (2nd & 3rd floors of the Learning Commons building) will undergo a major renovation project until the spring of 2026.

Project Overview

Most of the work will occur on the 3rd floor. The renovation will involve:

  • Replacing the roof and 3rd floor exterior windows
  • Reconfiguring interior spaces on the 3rd floor
  • Upgrading electrical, plumbing, and data infrastructure
  • Installing fire sprinklers on both floors
  • Renovating restrooms on both floors
  • Widening of stairwell doorways on the second floor

Specific improvements include improving access to the 3rd floor by opening up the stairwells, improving lighting on the 3rd floor, improving soundproofing, building new group study rooms on the 3rd floor, improving staff offices, building an archives facility, and ʻŌlelo Hawaiʻi signage.

Impacts to Services and Resources

The 3rd floor will be closed until the completion of the project. Select library materials have been relocated to the 2nd floor. The bulk of the library's collections have been put in storage and will be unavailable for the duration of the project. All e-book collections will remain available. The DVD collection will remain available.

When searching in the Primo Library Catalog, books in the results list that say "Check for available services" are books that are in storage and thus unavailable. Many of those books are also owned by other UH libraries, and often can be requested.

The 2nd floor restrooms are closed. There are no restrooms available in the Learning Commons. The nearest restrooms are in the LA and PS buildings.

Group study rooms are unavailable, due to the need to relocate services and staff into those spaces.

Construction noises and smells can sometimes be heard and smelled on the 2nd floor.

Updated September 9, 2025
 

What's New?

The installation of fire sprinklers on the 2nd floor is complete. Library and tutoring services will return to the Learning Commons building for Fall 2025.

Thank You!

Our deepest gratitude to everyone who have so generously helped us pack our books for storage during the renovation!

  • Garrett Chaves
  • Pi'ikea Hardy-Kahaleoumi
  • Shari Imanaka
  • Rachael Inake
  • Kelly Kennedy
  • Joy Lane
  • Melinda Lee
  • Meredith Lee
  • Lori Lum
  • Susan Lum
  • Nikki Manuel
  • Michael Oishi
  • Lilian Rebamonte-Smith
  • Brandi Reyes
  • Leanne Riseley
  • Erin Thompson
  • Jennifer Wharton
  • Tasha Williams Moses
 

Informational Presentation

Additional details are in this slide presentation that was shared with the campus community. You have to be logged in with a UH Google account to view the slides.

Timeline

May 2024
Award of contract
Summer 2024
  • Select print materials to keep available during construction.
  • Pack bulk of collections for storage
Fall 2024
  • Remove book shelving.
  • Relocate/store furniture
  • Relocate staff to alternate office space
Library vacates the 3rd floor by December 20
December 2024
Construction begins
May 19-July 2025
2nd floor closes for fire sprinkler installation.
August 2025
2nd floor reopens
March 2026
Staff, furniture, collections move back into renovated spaces
Timeline updated Apr. 29, 2025